Salient Features of the Project

Project Title Project: Four Laning of NH-39 (old NH-75) from Design Km 97+600 (Existing Km 96+740) (Udaipura Village) to Design Km 147+540 (Existing Km 148+020) (Bhogu Village) in the State of Jharkhand on Hybrid Annuity mode. (Package - II)
NH No.(New/Old) NH-39/NH75
Mode of the Execution (BOT Toll/BOT Annuity/EPC/HAM/Item Rate/Other) HAM
Length of the Project (in km) 49.940 (4 Lane Length)
Total Bid Project Cost (in Cr.) Rs. 908 Cr.
No. of Bypasses (Name of Town, Length) 3 (Latehar-10.8Km, Manika 5.05 Km, Bakoriya Sadbarba-12.55 Km)
No. of Major Bridges (Number and Location) 01 (at km 120+087)
DPR Consultant Name L N M Infra Project Group Pvt. Ltd.
Concessionaire Name (SPV & Parent Company ) M/s DRA BAIDYANATH HIGHWAYS PVT. LTD.
Date of Award (LOA Date) 29.03.2023
Appointed Date 09.10.2024
Construction Period (in Days) 730 Days
O&M period (in Days) 15 Years
Scheduled Date of completion 09.10.2026
Safety Consultant Indian Infratech Pvt. Ltd.
Independent Engineer M/s ALMONDZ GLOBAL INFRA CONSULTANT LIMITED IN Jv WITH GEO DESIGNS & RESEARCH PVT. LTD.
IE Agreement Date 05-04-2024
IE Mobilization Date 17-06-2024