| Project Title |
Project: Four Laning of NH-39 (old NH-75) from Design Km 97+600 (Existing Km 96+740) (Udaipura Village) to Design Km 147+540 (Existing Km 148+020) (Bhogu Village) in the State of Jharkhand on Hybrid Annuity mode.
(Package - II) |
| NH No.(New/Old) |
NH-39/NH75 |
| Mode of the Execution (BOT Toll/BOT Annuity/EPC/HAM/Item Rate/Other) |
HAM |
| Length of the Project (in km) |
49.940 (4 Lane Length) |
| Total Bid Project Cost (in Cr.) |
Rs. 908 Cr. |
| No. of Bypasses (Name of Town, Length) |
3 (Latehar-10.8Km, Manika 5.05 Km, Bakoriya Sadbarba-12.55 Km) |
| No. of Major Bridges (Number and Location)
|
01 (at km 120+087) |
| DPR Consultant Name |
L N M Infra Project Group Pvt. Ltd. |
| Concessionaire Name (SPV & Parent Company ) |
M/s DRA BAIDYANATH HIGHWAYS PVT. LTD. |
| Date of Award (LOA Date) |
29.03.2023 |
| Appointed Date |
09.10.2024 |
| Construction Period (in Days) |
730 Days |
| O&M period (in Days) |
15 Years |
| Scheduled Date of completion |
09.10.2026 |
| Safety Consultant |
Indian Infratech Pvt. Ltd. |
| Independent Engineer |
M/s ALMONDZ GLOBAL INFRA CONSULTANT LIMITED IN Jv WITH GEO DESIGNS & RESEARCH PVT. LTD. |
| IE Agreement Date |
05-04-2024 |
| IE Mobilization Date |
17-06-2024 |